1NextGen Electrolysis - Blending Equipment
Published
Description
WWU require a supplier to design and install a hydrogen blending unit and associated equipment to blend up to a maximum of 20% hydrogen by volume into the customers' existing natural gas supply. The injection will take place downstream of the meter where the end use is combustion to provide heat to the customers existing process. The customer process in non-interruptible and should the blend ratio go above the maximum allowable or if there is any failure of the hydrogen supply the blending infrastructure must be able to revert to 100% natural gas in order to maintain supply to the customer. The blending infrastructure will need to be able to meet the requirements set out in the scope. These requirements are taken from the recently published FUNCTIONAL SPECIFICATION FOR HYDROGEN BLENDING INFRASTRUCTURE a copy of which can be found in Appendix 1 in the scope. WWU will own and operate the hydrogen blending unit and any associated equipment which will be located at the customers site in line with Model 2 in the functional blending spec. Lot 1: Lot 1 Equipment Supply only Blending equipment Natural gas inlet: Pressure: 75 mbar inlet, Temp: -5 to 40 C, Max consumption: Daily - 25384.11 kWh, Max consumption: ½ Hourly - 1191.88 kWh, Mean consumption: Daily - 20175.21 kWh, Mean consumption: ½ Hourly - 435.96 kWh Hydrogen: Max H2 production: 45scmh (4.5kgH2/hr), Pressure: 2 to 7 bar from electrolyser but will be reduced to match the NG inlet, Temp: 60C from electrolyser but short run of pipe to blending tee so -5 to 60C Blended outlet: Injection into existing 3" steel pipework at 75 mbar The blending unit will be required to blend up to a maximum of 20% hydrogen by volume into the customers' existing natural gas supply. The injection will take place downstream of the meter where the end use is combustion to provide heat to the customers existing process. The customer process in non-interruptible and should the blend ratio go above the maximum allowable or if there is any failure of the hydrogen supply the blending infrastructure must be able to revert to 100% natural gas in order to maintain supply to the customer. The blending infrastructure will need to be able to meet the requirements set out in the below Requirements section. These requirements are taken from the recently published FUNCTIONAL SPECIFICATION FOR HYDROGEN BLENDING INFRASTRUCTURE. WWU will own and operate the hydrogen blending unit and any associated equipment which will be located at the customers site in line with Model 2 in the functional blending spec. FUNCTIONAL REQUIREMENTS HYDROGEN PRESSURE REGULATION AND METERING Hydrogen pressure regulation and control is required to ensure there is sufficient pressure at the point of injection into the customers system. Pressure regulation and control shall be to IGEM/TD/13 and or IGEM/TD/23. Hydrogen volume and energy flowrate are required and the metering system shall be appropriate for hydrogen that is compliant with Table 5 of IGEM/H/1 and Table 2 of PAS 4444. ACCURACY The hydrogen metering system should meet the accuracy requirements of Table 2 of the Functional Blending Specification in Appendix 1. HYDROGEN/GCV CONTROL Hydrogen injection rate shall be controlled so as to achieve: a minimum gross calorific value of gas at the comingled point a hydrogen content of the blend that is no greater than a maximum of 20% by volume a Wobbe index of the blend that is no less than the lower Wobbe limit permitted by Schedule 3 of the GSMR.GAS SAMPLING AND ANALYSIS HYDROGEN SUPPLY Gas sampling and analysis shall continuously or continually monitor the hydrogen supplied to the hydrogen blending unit . COMINGLED POINT Gas sampling and analysis shall continuously or continually monitor the blend at the comingled point and provide confirmation that it is compliant the minimum requirements agreed with WWU. A schedule of parameters that shall be monitored is given in Table 1 of the Functional Blending Specification. Calorific value shall be determined using an instrument approved by Ofgem for determination of calorific values for the purposes of determining the reference point against which flow weighted average calorific value (FWACV) capping shall apply. The instrument shall comply with the requirements listed in an appropriate Letter of Approval from Ofgem. ACCURACY The gas analysis system(s) shall meet the accuracy requirements of Table 3 of the Functional Blending Specification in Appendix 1. REMOTELY OPERATED VALVE A Remotely Operated Valve (ROV) shall be supplied, which shall be capable of manual remote or automatic closure in the event of variation in blend outside of the agreed conditions or inability to provide sufficient blending where this is practiced. A more detailed description of trip and reset philosophy is given in the Gas Quality and Supervisory system functional block. The means of actuation of the ROV shall be the choice of WWU. FWACV FUNCTIONALITY The system shall deliver the functionality required for the FWACV regime, namely requirements set out in the Gas (COTE) Regulations. Conditions currently specified include the following: Acquisition and storage of gross CV of the supplied hydrogen from the approved CV determination device, together with a flag indicating its quality/suitability for use. For non-continual CV determination devices, the System - CV determination device interface shall be such that only one value of each CV determination is acquired. Acquisition and storage of instantaneous volumetric flowrate of hydrogen at the time of acquisition of gross CV. Initiation of daily calibration of CV determination device. Automated tests of apparatus and equipment at periods not exceeding 35 days in accordance with Regulation 6(e) of the Gas (COTE) Regulations. The facility to manually initiate tests of apparatus and equipment either by, or at the request of, the Gas Examiner. Provision of a report of results of automated or manual tests in accordance with Regulation 6(e) of the Gas (COTE) Regulations. Calculation of the daily average CV of the hydrogen at the end of each Gas Day in the manner specified by the Letter of Direction or by WWU depending on site specific conditions. This will require confirmation of the quality of individual records (records are Good if the CV determination device is operating within agreed limits) and averaging of only those records that are Good and for which gas is flowing past the sample point. In addition, a flag shall be stored indicating whether the resulting daily average CV is Valid (i.e., the maximum time between Good records is less than 8 hours). Gross CV values during calibration or tests of apparatus and equipment shall not be included for averaging. Acquisition and storage of integrated daily volume at the end of the Gas Day. In addition to local storage of individual data acquired, appropriate means of secure transfer of data to WWU Any software and hardware solutions are acceptable provided they deliver the required FWACV functionality, but WWU will require demonstration that the required functionality has been delivered. GAS QUALITY AND SUPERVISORY SYSTEM The Gas Quality and Supervisory system shall monitor hydrogen and blend quality signals from the hydrogen blending unit instrumentation, the remote monitoring unit instrumentation and the delivery facility instrumentation. Monitoring shall be continuous or continual and provide confirmation that the blend at the comingled point is compliant with the requirements set out by Table 1 of the functional blending specification. In the event of an excursion in any of the parameters or any other parameters agreed by risk assessment (see 6.2 in the full blending specification document) the trip system shall initiate closure of the ROV on the hydrogen feed and prevent further injection of hydrogen into the customer process. The system should revert to a pure natural gas feed to ensure that customer operations are not interrupted. The limit values in the parameters of Table 1 are indicative and site-specific values shall be agreed during design approval and may be subject to review if risk assessment confirms such a requirement (see 6.2 in the full blending specification document). All alarms and trips shall therefore be configurable. If closure of the ROV has been initiated because of non-compliance with the parameters in Table 1 or any other parameters agreed by risk assessment (see 6.2 in the full blending specification document ), then its subsequent opening shall be under the sole control of WWU. DESIGN APPROVAL ASSETS OWNED BY WWU Design approval for all assets owned by WWU shall be managed in accordance with IGEM/GL/5 and T/PM/GL/5. TESTING ASSETS OWNED BY WWU Pressure testing of all pressure containing components and systems shall be carried out in accordance with Management/Work Procedure PT/1 pertaining to WWU. Testing of electrical and instrument systems and equipment shall be carried out in accordance with BS 7671 and BS EN 60079-14. COMMISSIONING AND INITIAL VALIDATION GENERAL REQUIREMENTS All personnel carrying out commissioning and initial validation shall be competent and adequately trained to do so. A written commissioning procedure shall be agreed and shall take into account relevant Permit to Work procedures. Initial validation shall be carried out in order to demonstrate the accuracy of the measurement system complies with the requirements of Table 2. Suitable systems, software or procedures shall be provided or agreed to ensure that compliance can be demonstrated. ASSETS OWNED BY WWU Following satisfactory commissioning, validation of the flow and gas quality measurement system shall be carried out in accordance with the relevant parts of T/PR/ME/2 or an alternative documented procedure if appropriate. OPERATION CONTROL AND MONITORING OF CALORIFIC VALUE The requirements for control and monitoring of calorific value shall be agreed in the with WWU. WWU shall at appropriate intervals calculate an appropriate target CV so as to minimise the risk of FWACV capping and communicate its value to the DFO and the hydrogen blending unit. The hydrogen injection flowrate shall be controlled so as to ensure that instantaneous CV at the comingled point does not fall below the prevailing target CV, subject to: hydrogen content of the gas at the comingled point shall not be greater than that permitted by WWU Wobbe index of the gas at the comingled point shall not be less than that permitted by the WWU. CONTROL AND MONITORING OF GAS QUALITY Gas Quality of the gas at the comingled point shall be monitored so as to ensure compliance with the requirements set out by WWU. The frequency of monitoring shall be determined though measurement risk assessment. The supplier will also need to consider : • Carry out a full Hazid/Hazop for integration into the whole system. • Identify the impact on the downstream process • Any potential storage needed to require a consistent blend Not required • Odorant injection Lot 2: Equipment Supply & Install Complete Connect electrolyser to inlet of blending equipment via designed pipework. Connect existing natural gas pipework into blending equipment inlet. Connect blending equipment outlet to the customers' existing gas service , downstream of the meter Carry out all civils for the Hydrogen blending equipment and pipework. Note : WWU reserve the right to carry out Work package 2 to inform future learnings of the gas networks activities.
Timeline
Publish date
16 days ago
Close date
in 14 days
Buyer information
Wales & West Utilities Ltd
- Email:
- nicci.birchall@wwutilities.co.uk
Explore contracts and tenders relating to Wales & West Utilities Ltd
Go to buyer profileNotice topics
Source
"Find-a-Tender"To save this opportunity, sign up to Stotles for free.
Save in appTender tracking
Access a feed of government opportunities tailored to you, in one view. Receive email alerts and integrate with your CRM to stay up-to-date.
Proactive prospecting
Get ahead of competitors by reaching out to key decision-makers within buying organisations directly.
360° account briefings
Create in-depth briefings on buyer organisations based on their historical & upcoming procurement activity.
Collaboration tools
Streamline sales workflows with team collaboration and communication features, and integrate with your favourite sales tools.
Explore similar tenders and contracts
Browse open tenders, recent contract awards and upcoming contract expiries that match similar CPV codes.
- Openclosing
Provision of Medical Gas Pipe Maintenance Services
Northern Care Alliance NHS Foundation TrustPublished 11 days ago
- Openclosing
Provision of Medical Gas Pipe Maintenance Services
Northern Care Alliance NHS Foundation Trust1 GBPPublished 11 days ago
- Unknown
Mathematics & Statistics: Rotating Table & Control for Fluid Mechanics Experiments
School of Mathematics & StatisticsPublished 30 days ago
- Closed
Rotating Table & Control for Fluid Mechanics Experiments
University of St AndrewsPublished 30 days ago
- Openclosing
Palladium Permeators and Palladium Membrane Reactors
United Kingdom Atomic Energy Authority1,000,000 GBPPublished a month ago
Explore other contracts published by Wales & West Utilities Ltd
Explore more open tenders, recent contract awards and upcoming contract expiries published by Wales & West Utilities Ltd.
- Closed
Health and Safety Risk Management
Wales & West Utilities Ltd3,000,000 GBPPublished 8 months ago
- Closed
GD3 Gas Mains Replacement and Reinstatement
Wales & West Utilities Ltd420,000,000 GBPPublished 10 months ago
- Closed
Design & Build: Industrial Control System (ICS) Network
Wales & West Utilities LtdPublished 11 months ago
- Closed
Accelerate decarbonisation and consumer vulnerability projects
Wales & West Utilities LtdPublished a year ago
- Closed
WWU1342 - Fixed Line VOIP & Redbox Replacement
Wales & West Utilities Ltd300,000 GBPPublished a year ago
- Closed
Call for projects under the Vulnerability and Carbon Monoxide Allowance (VCMA)
Wales & West Utilities Ltd12,000,000 GBPPublished a year ago
Explore more suppliers to Wales & West Utilities Ltd
Sign upExplore top buyers for public sector contracts
Discover open tenders, contract awards and upcoming contract expiries of thousands of public sector buyers below. Gain insights into their procurement activity, historical purchasing trends and more.
Explore top sources for public sector contracts
Stotles aggregates public sector contract data from every major procurement data source. We ingest this data and surface the most relevant insights for our users. Explore our list of public sector procurement data sources below.